Ready between tenants
A unit turned over and made move-in ready to a date — repair, paint, flooring and a final clean, sequenced so nothing collided.

01 The goal
Turn a unit over and hand it back move-in ready on an agreed target window between tenancies.
- A hard target window set by the incoming tenancy
- An occupied building — access limited to daytime hours
- Flooring could not begin until repairs passed a check
02 Named participants
Every business expected on site is named before work begins — disclosure, not pre-verification by the Collective.
03 Work packages
Each package has exactly one accountable owner — never “the team.”
04 Sequencing challenge
Flooring could not start until repairs passed a paint-ready check, and paint could not start on unfinished walls — three packages on one short window with no room for a collision.
05 Key decision
The landlord approved a paint allowance up front, before scheduling, so the finishing package could be booked against the window instead of waiting on a later selection.
06 A recorded change
Opening one wall for repair revealed older water damage. Work paused; sealing and repainting the affected wall were written up as a versioned change with its own price, and the package continued only once the landlord accepted it — no surprise on the final invoice.
The approved budget carried the paint allowance as a named line with its selection deadline. The allowance was reconciled to the actual selection at closeout — a TBD never silently became a charge.
07 Milestones
- Brief acceptedGoal, target window and constraints recorded.
- Site assessmentScope confirmed on site; packages and owners set.
- Scope & budget approvedPlan v2 approved with the paint allowance.
- Repairs passed checkPaint-ready check cleared; finishing released.
- Packages completedFinishing, flooring and clean completed in sequence.
- Deficiency review & sign-offPunch list cleared; landlord signed off before the final invoice.
08 Result & sign-off
Move-in-ready on the agreed target window, with every party named and every change recorded.
Completion. All four packages completed and confirmed; the closeout record listed the final participant list, the approved change and the reconciled budget.
Deficiencies. Two minor deficiencies (a touch-up and a transition strip) were recorded, assigned, completed and accepted before sign-off.
Put every moving part on one shared plan.
Share the goal and constraints. Shared Plan confirms fit, then draws a plan with named parties, sequence and budget — for you to approve before anything is scheduled.