Deck & fence package
Exterior work across parties on one tight site — deck repair, fence and site cleanup, sequenced by disclosed access windows.

01 The goal
Coordinate a deck repair, a fence and a site cleanup across parties sharing one narrow site, ending in a clean hand-off.
- A single narrow site two providers had to share
- Fence work blocked the only access the deck package needed
- Weather-dependent finishing that could not be promised to a date
02 Named participants
Every business expected on site is named before work begins — disclosure, not pre-verification by the Collective.
03 Work packages
Each package has exactly one accountable owner — never “the team.”
04 Sequencing challenge
Both providers needed the same narrow side access, and the fence work sat directly across the route the deck package used — so the two could not simply run in parallel.
05 Key decision
Sequenced access windows were disclosed up front: each provider had a named window on the shared site, agreed before either started, so the tight site never became a collision.
06 A recorded change
One deck post footing was found more degraded than expected. Replacing it was written up as a versioned change with its own price and accepted before the deck package continued.
The budget carried the deck and fence packages as named totals with a small contingency the homeowner had explicitly approved — the footing change was drawn from it transparently, not silently.
07 Milestones
- Brief acceptedGoal and shared-site constraint recorded.
- Site assessmentPackages, dependencies and access windows set.
- Scope & budget approvedPlan approved with a named contingency.
- Access windows runEach provider worked its disclosed window.
- Change approvedFooting change priced and accepted.
- Cleanup & sign-offSite cleaned; homeowner signed off.
08 Result & sign-off
A clean handoff and a signed-off closeout, with a shared site sequenced by disclosed windows rather than left to chance.
Completion. All packages completed; the closeout recorded the access sequence, the approved footing change and the final budget.
Deficiencies. One deficiency (a gate alignment) was recorded, completed by the responsible provider and accepted before sign-off.
Put every moving part on one shared plan.
Share the goal and constraints. Shared Plan confirms fit, then draws a plan with named parties, sequence and budget — for you to approve before anything is scheduled.